Bidders are required to submit tender documents outlining their proposed approach to the project, including logistics, technical design, company structure, examples, and references from previous projects, as well as cost.
				    In parallel, new environmental classification rules for wind and solar projects, measures to address congestion of the local grid through the imposition of injection curtailments by the competent operators and, lastly, the
				    From 2018 to 2022, solar capacity in the Mediterranean country grew from 2.6 to 5.3 gigawatts, whereas wind installations increased from 2.8 to 4.7 megawatts.
				    Greece has set more ambitious targets for expanding solar and wind power to cut greenhouse emissions by 2030 under a revised energy and climate plan presented on
				    To meet these updated targets, an estimated €95 billion ($104 billion) in additional investment will be needed by 2030, funding initiatives like energy efficiency in buildings, expansion of solar and wind capacity, and
				    Households and companies in Greece may see a decline in electricity tariffs after the latest auction of solar and wind capacity. Regulators accepted offers from power plant operators for a total of 141.9 MW and 471.8
				    The upgraded target will be aligned with Greece''s enhanced ambitions for renewable energy deployments through 2030. While previously the NECP called for Greece to
				    The average subsidy price in the third auction exercise came at €52589.16/MW/year. The lowest successful bid stood at €43927/MW/year, concerning a 25
				    New offshore wind regulatory framework published The ministry''s much awaited regulatory framework for offshore wind has been submitted for public consultation after a delay
				    Winning bids in first generation tender in NSW were pitched at little more than half their levellised cost of energy, while the battery project promised a lot more storage.
				    Greece has awarded 502.94 MW of wind and solar power capacity in its latest mixed renewables tender, with bids hitting as low as EUR 49.11 (USD 53.06) per MWh.
				    Discover how Greece is rapidly expanding its clean energy sector with significant investments in solar and wind farms to achieve ambitious sustainability goals.
				    The EU executive approved on Tuesday under EU State aid rules Greece''s request to offer financial help for two solar energy projects in the country that are expected to
				    The average subsidy price in the third auction exercise came at €52589.16/MW/year. The lowest successful bid stood at €43927/MW/year, concerning a 25 MW/100 MWh project in the Western Macedonia region. The
				    Summary November 2023, Greece submitted its NECP with more ambitious and updated targets for renewables and solar: 23.5 GW for all forms of renewables, from which 13.4 GW came from
				    RWE intends to maintain the pace of investment with an ambition to invest up to €8 billion net from 2024 to 2030 in new UK clean energy infrastructure which, this year alone,
				    Record-low ₹3.32/unit tariff set for solar + 4-hr energy storage projects in SJVN auction, 5.8% lower than SECI''s Dec 2024 rate.
				    By increasing wind''s role, Greece could reduce power import costs and avoid curtailment of surplus solar, delivering cheaper and more reliable electricity to consumers.
				    Italy accelerates the transition to renewable energy Italy is stepping into a new energy era with the MACSE auction in early 2025. Underpinning MACSE, or Meccanismo di
				    Government Initiatives and Auctions Greece has already taken steps towards meeting its storage goals by launching auctions for battery storage projects. The first 1,000 MW of battery storage systems are in progress, with
				    Major constraints remain in grid capacity and storage, but these gaps also create lucrative opportunities for integrated PV+storage projects, offshore wind developers, and
				    The first tender in August resulted in an average price of €49.748/MW per year, while the lowest successful bid was €33.948/MW per year. The highest successful bid was €64.122/MW per year.
				    It is forecast that 210,000 new jobs will be created each year from 2025. The plan is divided into three sub-periods. The first, in 2025-2030, foresees the continued, rapid penetration of wind
				    This is an extract from a report " SolarPower Europe (2023): EU Market Outlook for Solar Power 2023-2027" prepared by Solar Power Europe. In this extract we specifically focus on Spain, France and Greece. Spain
				    The rapid growth of Greece''s storage market is driven by a combination of factors, including Greece''s heavy reliance on fossil gas which has led to high price volatility, ambitious energy
				    The European Commission has approved €1 billion ($1.08 billion) of Greek measures under EU state-aid rules to support two utility-scale solar projects with lithium-ion batteries and molten-salt
				    The revised 2030 Energy & Climate plan estimates that an additional investment of €95 billion is needed by 2030 to scale up energy efficiency, solar, wind and energy storage projects.
				    Jinko ESS, the global leading energy storage company recently announced the successful signing of a 100MWh energy storage project with a key client in Greece. The project
				    According to the Energy and Environment minister, Greece''s 2030 revised renewable energy goal is now set at 28 GW plus 7 GW of storage. Energy and Environment minister Kostas Skrekas announced yesterday that
				    As Greece accelerates toward a renewable energy future by 2030, wind power''s role is expanding from the mountaintop wind farm to the factory floor. The integration of wind
				    A total of 1,201 GWh of bids were submited of which 220 GWh was successful from a hybrid onshore wind-solar PV facility. The auction model is based on a one-sided sliding premium
				    According to the Energy and Environment minister, Greece''s 2030 revised renewable energy goal is now set at 28 GW plus 7 GW of storage. Energy and Environment
By 2030, Greece wants to build at least 2 GW of offshore wind. Given the characteristics of Greek waters, much of it will be floating offshore wind farms. The law appoints the state-owned exploration company Hellenic Hydrocarbon Resources & Energy Resources Management to lead site investigation and allocation and concession development.
The maximum prices are the same as in last year’s auction for domestic projects. As for the auctions to take place in 2023, the prices were set at EUR 70 per MWh for PV and at EUR 83 per MWh for wind farms. Investors that win at the joint tenders will have a maximum of 36 months to realize wind projects and 30 months for PV.
As for the auctions to take place in 2023, the prices were set at EUR 70 per MWh for PV and at EUR 83 per MWh for wind farms. Investors that win at the joint tenders will have a maximum of 36 months to realize wind projects and 30 months for PV. In the case of special auctions, the time is set at 23 months for solar power and 24 months for wind.
Investors that win at the joint tenders will have a maximum of 36 months to realize wind projects and 30 months for PV. In the case of special auctions, the time is set at 23 months for solar power and 24 months for wind. For projects combining renewables and storage, the available time is 36 months for wind and 30 for PV.
The highest successful bid was €64.122/MW per year. Helleniq Energy secured three projects (100 MW), Intra Energy secured another three projects (100 MW), PPC Renewables won two projects (98 MW), Energy Bank secured a 50 MW project, and Mytilineos Group's Aenaos won a 48 MW battery contract.
Additionally, an application fee of €2,500 per submission to the regulator is required. A 100% tender subscription rule fosters competition, requiring at least 576 MW of energy storage capacity to vie for selection to secure 288 MW.