The Project will include a solar power plant with 218,805 solar panels, generating up to 105 MW of electricity. Other key parts of the Project include underground cables, a substation to increase
Oman - The first Final Investment Decision (FID) is anticipated during the 2026-27 timeframe by one of the consortiums awarded mandates to develop green hydrogen (GH2) projects in the Sultanate of Oman.
Oman''s Nama Power and Water Procurement Co. received four bids from companies and consortia looking to develop the 500 MW solar project in Ibri, northwestern Oman.
Oman''s Nama Power and Water Procurement Company has revealed the list of companies that have officially submitted bids for the 500 MW Ibri III Solar Project, to be located in Al Dhahirah Governorate.
Oman - The first Final Investment Decision (FID) is anticipated during the 2026-27 timeframe by one of the consortiums awarded mandates to develop green hydrogen (GH2)
Oman''s Nama Power and Water Procurement Company (PWP) has announced that four energy companies are in the final stage of bidding for the 500-megawatt (MW) Ibri III Solar Independent Power Project (IPP).
The first Final Investment Decision (FID) is anticipated during the 2026-27 timeframe by one of the consortiums awarded mandates to develop green hydrogen (GH2)
Nama Power & Water Procurement, Oman announces the list of bidders who submitted bids for the development of Ibri III Solar IPP, in Ibri in Al Dhahirah Governorate.
The project will be located alongside the 500 MW Ibri II Solar Project, commissioned by the ACWA Power-led consortium in 2022 (see Oman Reveals Shortlisted
Covering an area of 32.5 hectares in the second phase of the Freezone, the project is anticipated to deliver an annual production capacity of 6 gigawatts of solar cells and 3 gigawatts of solar modules. Operations are
The Omani authorities aim to develop a 500 MW solar project in Ibri, in northwestern Oman, where other PV facilities are located. It will be commissioned by the fourth quarter of 2026.
The Manah 1 project, in line with the "Oman Vision 2040" will increase power generation capacity through renewable independent power projects.
In January 2024, Oman launched a public tender for another 500 MW solar project, Ibri Solar III, with commercial operations due to begin in the fourth quarter of 2026.
Oman Solar Systems Co. LLC (OSS), based in the Sultanate of Oman, we provide "Power Solutions" with ''State of the art'' technology in the fields of Stand-by Power Systems and Renewable Energy Solutions.
The developments are North Solar, a 100 MW solar project located in Saih Nihaydah in northern Oman, and Riyah-1 and Riyah-2, two 100 MW wind projects located in
The 500MW Ibri II photovoltaic (PV) solar power project located in the Ad-Dhahirah region will be the first utility-scale renewable energy facility in Oman.
Oman''s construction sector is experiencing a resurgence in 2024, poised to shape the country''s future with a wave of exciting upcoming projects. This growth is fueled by a confluence of factors. The government is actively investing in
Nama Water and Energy Procurement announced the qualified companies for the "Ibri 3" solar power project in Oman. This 500 MW project, costing around OMR 155
The solar park will be built in Al Dhahirah Governorate adjoining the Ibri II, Oman''s first 500-MW solar project. Ibri III is slated for commissioning in the last quarter of 2026.
In a key development, Oman Power and Water Procurement Co. (OPWP) has come up with a tender to select the independent power producers (IPPs) for the development of a 500 megawatt (MW) solar energy park.
Oman – The first Final Investment Decision (FID) is anticipated during the 2026-27 timeframe by one of the consortiums awarded mandates to develop green hydrogen (GH2) projects in the Sultanate of Oman.
Phase one of the project has completely sold out, with 55% of buyers being Omani nationals. Yiti, Oman''s Sustainable City Announces Project Completion by 2026. Diamond Developers, MEP, oman, Omran, project, SEE
Oman launches tender for 500-MW Ibri III Solar PV IPP, with a submission deadline of February 19. The project is estimated to cost OMR 155 million and is expected to be operational by Q4
OMAN AT A GLANCE * E&P = Engineering and procurement; EPC ITB = Engineering, procurement and construction invitation to bid: FEED = Front-end engineering and design.
North Solar, a 100 MW solar project, located in Saih Nihaydah in northern Oman; Riyah-1 and Riyah-2, two 100 MW wind projects, located in Amin and West Nimr fields in southern Oman.
MUSCAT: In one of its biggest capacity procurements to date, Nama Power and Water Procurement Company (PWP) – the sole procurer of new power generation
Looking ahead, Oman''s commitment to expanding its solar power infrastructure remains steadfast. The Ibri 3 project is expected to serve as a catalyst for more innovative
PROJECTS AT A GLANCE * E&P = Engineering and procurement; EPC ITB = Engineering, procurement and construction invitation to bid: FEED = Front-end engineering and design;
The Manah 1 project, in line with the "Oman Vision 2040" will increase power generation capacity through renewable independent power projects.
This utility-scale solar photovoltaic farm, which is scheduled to be commercially operational in Q2 2026, marks a major milestone in PDO''s renewable energy journey. By harnessing solar
Additionally, PDO is finalizing plans for a 100 MW solar PV-based IPP, named the ‘North Solar Storage IPP,’ set to include Oman’s first battery energy storage system (BESS). This BESS, using lithium-ion battery technology, will store electrical energy and supply a maximum of 100 MW peak power to PDO’s grid during daylight hours.
The Company earlier notified that, the procurement of this solar project is part of the Sultanate of Oman’s government policy to diversify energy resources to meet the growing demand for electricity.
A consortium of Abu Dhabi Future Energy Company (Masdar), Korea Midland Power (KOMIPO) and Al Khadra Partners makes up the first listed bid, while a partnership between ACWA Power and TotalEnergies Renewables forms the second bid.
PWP kicked off the tender in January 2024. It received twelve submissions from local and international developers, with nine applications qualifying to submit proposals in June last year. The Ibri III solar project, with an estimated project cost of OMR 155 million ($402.6 million), has a scheduled completion date of the first quarter of 2027.